WAIPUKURAU OVERBRIDGE

As main contractor Russell Roads undertook Stage 1 of the replacement of the Waipukurau Overbridge. 

The contract value ended up at just under $1 million and included cut to fill on site off 9,000m3 and borrow to fill of 60,000m3 of river run.  This was sourced from a river bed 12 kms from the site.

Also involved was the construction of a concrete walkway.

Even though the contract was mostly carried out through the winter months, it was completed on time and enabling the client to carry on with Stage 2.

Back to Projects >>